Home  >  Investors  >  Annual Report  >  Latin America & Asia Pacific

Latin America & Asia Pacific

Annual Report 2024

Latin America and Asia Pacific

Barrick’s Latin America and Asia Pacific portfolio comprises operations and projects in South America, the Dominican Republic, Pakistan, and Papua New Guinea.

This region is central to Barrick’s growth strategy, with the successful restart of Porgera, the progress of the Pueblo Viejo Expansion, and the addition of 13 million ounces of gold and 7.3 million tonnes of copper to attributable reserves from the Reko Diq project.

Latin America and Asia Pacific 5-Year Production Outlook Gold equivalent ounces calculated from our copper assets are calculated using a gold price of $1,400/oz and copper price of $3.00/lb. Barrick’s five-year indicative outlook is based on our current operating asset portfolio, sustaining projects in progress and exploration/mineral resource management initiatives in execution. This outlook is based on our current reserves and resources and assumes that we will continue to be able to convert resources into reserves. Additional asset optimization, further exploration growth, new project initiatives and divestitures are not included. For the company’s gold and copper segments, and where applicable for a specific region, this indicative outlook is subject to change and assumes the following: new open pit production permitted and commencing at Hemlo in the second half of 2025, allowing three years for permitting and two years for pre-stripping prior to first ore production in 2027; Tongon will enter care and maintenance by 2027; and production from the Zaldívar CuproChlor® Chloride Leach Project (Antofagasta is the operator of Zaldívar). Our five-year indicative outlook excludes production from Fourmile, as well as Pierina and Golden Sunlight, both of which are currently in care and maintenance; and production from long-term greenfield optionality from Donlin, Pascua-Lama, Norte Abierto and Alturas. Barrick’s five-year and ten-year production profile in this annual report also assumes an indicative gold and copper production profile for Reko Diq and an indicative copper production profile for the Lumwana Super Pit expansion, both of which are conceptual in nature.

The chart shows stacked bar graphs representing gold production in thousands of ounces (koz) for multiple mining operations (Pueblo Viejo, Veladero, Porgera, Reko Diq) and copper production (GEO) from 2024 to 2029. The left y-axis shows values from 0 to 1,800 koz, while the right y-axis shows costs from 0 to $1,600/oz. Four trend lines track gold cost metrics: Cost of sales (green), Total cash costs (light green), AISC (All-In Sustaining Costs - orange), and Total capital expenditures (blue). Gold production shows an increasing trend from about 800 koz in 2024 to 1,700 koz in 2029, with Pueblo Viejo providing the largest consistent production base. The AISC trend line shows a declining cost structure from approximately $1,400/oz to $1,000/oz over the period.

GEO from copper assets are calculated using gold price of $2,397/oz for 2024 and $1,400 for 2025 to 2029; and copper price of $4.15/lb for 2024 and $3.00/lb for 2025 to 2029. Copper produced at Reko Diq is included in GEOs.

The Pueblo Viejo gold mine in the Dominican Republic consists of two open pits, Moore and Monte Negro, with ore processed through autoclaves. The commissioning of the expansion project has been completed and the process plant is currently ramping up to achieve its design throughput, supported by additional throughput and recovery improvement projects scheduled for 2025. This expansion is expected to extend the mine's life beyond 2040 while maintaining average annual gold production above 800,000 ounces. The Naranjo Tailings Storage Facility project transitioned from feasibility study to execution following the successful completion of the study in Q3 2024. Meanwhile, the resettlement initiative for residents impacted by the Naranjo Dam footprint continues to advance, with numerous homes completed and several hundred more under construction. Exploration activities have consolidated new high-potential areas in the Dominican Republic, with geological fieldwork conducted in 2024 and field validation activities planned for 2025 to support further resource development.

At Veladero in Argentina, the mine exceeded its 2024 production guidance while remaining below the cost guidance threshold. The Phase 7B leach pad expansion was successfully completed at the end of 2024. The construction of the Phase 8 leach pad is set to start in Q1 2025 and completion expected by 2026. At the same time, exploration drilling continues in the Veladero district with a view to extend the current life of mine.

In Papua New Guinea, the recommissioning of Porgera was completed ahead of schedule with operations steadily ramping up despite significant logistical challenges. In response to the Mulitaka landslide disaster, which disrupted the primary access road to the Porgera Valley, interim solutions have been implemented while long-term infrastructure plans advance.

In Peru, Pierina remains an industry-leading example of environmental rehabilitation and closure is expected to be substantially completed in 2025. Generative exploration work continues across multiple targets to support growth in this country.

At Reko Diq in Pakistan, Barrick successfully completed the updated feasibility study in 2024, representing a major milestone in the development of one of the world's largest undeveloped copper-gold deposits. Once fully commissioned, the project is projected to deliver 240,000 tonnes of copper production and 297,000 ounces of gold per year during Phase 1, increasing to 460,000 tonnes of copper and 520,000 ounces of gold during the first 10 years (2034-2043) of Phase 2 (100% basis). First production is targeted for the end of 2028. In addition, the full project Environmental and Social Impact Assessment was submitted to the Balochistan Environmental Protection Agency during Q4 2024 and approval is expected in Q1 2025. With the completion of the updated feasibility study, early works construction began in Q1 2025 with a final investment decision expected later in 2025 to proceed with development of Phase 1, subject to joint venture approvals and the finalization of the project financing. Exploration and sampling activities continue to identify further growth opportunities in the area.