For Immediate Release
August 29, 2001…. Barrick Gold Corporation today advised that a slope movement occurred earlier today on the south all of the Betze-Post pit in Nevada. There was no impact on Barrick’s workforce, mining operations, production or reserves.
Barrick along with Newmont Mining Corporation, which separately operates the underground Deep Post Mine within the Betze-Post pit, had been jointly monitoring the affected area of the final pit wall over the last several months.
The event caused a temporary outage of a power line, which was restored within hours.
The movement occurred in an area where Barrick had completed mining and planned to use as a backfill site. As a result, production and reserves were not affected. Operations in the pit were not interrupted.
Investor Contact:
Richard Young
Vice President,
Investor Relations
Tel (416) 307-7431
Fax (416) 861-0727
Media Contact:
Vincent Borg
Vice President,
Corporate
Communications
Tel (416) 307-7477
Fax (416) 861-1509
Internet:
http://www.barrick.com
Barrick Gold Corporation
Royal Bank Plaza
South Tower, Suite 2700
Toronto, Canada
M5J 2J3